Why does nobody talk about ordering windows before the foundation is dug?

I used to wait until the framing stage to order windows, but that cost me 3 weeks of downtime on a build in Spokane last spring. Now I lock in window specs during the excavation phase, right after the soil test comes back. It sounds crazy to plan that far ahead, but lead times on custom sizes are running 10 to 12 weeks around here. Has anyone else shifted their ordering schedule earlier just to keep the crew moving?