That 2 minute phone call about the schedule sync saved our whole drywall phase
I was stuck on why the field crews kept seeing stale dates in our software and one superintendent in Austin told me to just check the timezone on the import file, and after fixing that one setting, our 40 unit project finally stopped having two different start dates for the same task, has anyone else had a stupid tiny setting like that mess up their whole rollout?