PSA: I just finished a 4,000 square foot slab in one day with a crew of three, which I thought was impossible for a broom finish.
We started at 4 AM, used a ride-on trowel for the first time, and the key was having one guy just handle the edges and corners with a magnesium float while the other two stayed on the machine, so if anyone has a better system for big pours I'd love to hear it.
3 comments
Log in to join the discussion
Log In3 Comments
riveradams26d ago
Man, my buddy tried that once and his ride-on sank into the mud. Total disaster.
6
rubyk8620d ago
Ouch, that sounds rough. How deep did his machine end up sinking?
3
phoenix_adams26d ago
Starting that early is smart to beat the heat. Did you do anything special with the subgrade prep to avoid the sinking issue @riveradams mentioned? A ride-on needs a really solid base. Also, what mix design were you running to get it to set up fast enough for a one-day finish?